BLOG · RAYSUN NEWS

Allocation keys for energy sharing: the rules in Wallonia, Flanders and Brussels

Published 12 October 2026 — RaYSun blog

Introduction

In an energy sharing operation, the electricity injected by producers is allocated to consumers quarter hour by quarter hour. The rule that sets this allocation is called the allocation key. It determines what each participant receives and, overall, how much energy the operation manages to share. The three Belgian Regions apply the same basic principles, but each has defined its own keys, its own number of calculation rounds and its own procedure for changing a key. This article first describes what is common, then the details for Wallonia, Flanders and Brussels. Pick your Region in the table of contents to go straight to the relevant part.

The rules common to the three Regions

Fixed key or dynamic key

All keys fall into two families.

Diagram comparing two allocation keys over the same quarter hour: with a fixed key in equal shares applied in one round, 73.3 kWh out of 100 are shared; with a key pro rata to consumption, all 100 kWh are shared
Fictitious example. A fixed key applied in a single round leaves some energy unshared; a pro rata key, or additional calculation rounds, redistribute it. Click to enlarge.

Between the two, the Regions allow the calculation to be repeated: an additional round redistributes the excess of the previous round to the participants that are not yet covered. This point, the number of rounds and the key used in each of them, is where the three Regions differ most.

In Wallonia

Framework. The rules are set at regional level by the electricity decree, the Walloon Government order of 17 March 2023 and the list of standard keys drawn up by CWaPE, the Walloon regulator. They apply to all grid operators: ORES, RESA, AIEG, AIESH and REW. WalloWatt is one of the energy communities managed by RaYSun. It is the main one in Wallonia: it hosts the largest number of sharing operations.

Three standard keys.

Up to three iterations. The calculation can be repeated at most three times per quarter hour. The second iteration allocates the excess of the first to the participants whose offtake is not fully covered, and the third does the same with the excess of the second. Each iteration has its own key. Two rules frame this choice.

Example. In one quarter hour, 100 kWh are injected and four participants take 10, 20, 40 and 60 kWh. In a single iteration, the equal key shares 80 kWh, a specific key that is poorly matched to consumption shares 60 kWh, and the pro rata key shares everything. The last calculation combines two iterations: A and B are served first and covered at 100%, then the excess is allocated pro rata between C and D.

Four calculations over the same quarter hour in Wallonia, for 100 kWh injected: equal fixed key, 80 kWh shared; specific fixed key, 60 kWh; dynamic pro rata key, 100 kWh; two iterations with priority, 100 kWh
Fictitious example. The three standard keys applied in one iteration, then a calculation in two iterations: participants A and B are served first, the excess goes to the others. Click to enlarge.

Non-standard key. A standard key is accepted by the grid operator. Another key can be proposed: the grid operator then examines its technical and economic feasibility, states the time needed to implement it and proposes an alternative key.

Declaration and changes. The key is declared in the sharing form, which states the number of iterations and the key used in each. To change it, the representative of the operation submits a modification form to the grid operator, which sends back an amendment to the agreement. For a simple change of standard key, the procedure provides up to 20 working days for sending the amendment, 10 working days for returning it signed, and entry into force on the 20th working day after it is received, which makes 50 working days at most. This change does not require a new authorisation from CWaPE. The authorisation must however be reviewed when participants are added, or when a production installation is added or removed; the maximum time then rises to 110 working days.

In Flanders

Framework. The rules are set out in the energy sharing protocol of Fluvius, the Flemish grid operator. The current version, 3.2, was approved in July 2024 by the Flemish regulator, the Vlaamse Nutsregulator (formerly VREG). SamenWatt is one of the energy communities managed by RaYSun. It is the main one in Flanders: it hosts the largest number of sharing operations.

Percentages per offtake point. The manager of the operation enters, for each offtake point, a percentage with at most two decimals. The total must be 100%. No percentage is assigned to injection points. The manager then chooses, for the whole group, one of the three types of key.

A rule specific to Flanders. A participant never receives its own injection. Yet a participant that both produces and consumes also has a percentage in the key. The difference between the first two keys lies in what happens to that percentage when its own injection is being allocated.

Example. In one quarter hour, A injects 80 kWh and B 20 kWh. B also consumes 30 kWh, C 20 kWh and D 60 kWh. The key gives 40% to B, 30% to C and 30% to D.

Three calculations over the same quarter hour in Flanders, for 100 kWh injected by A and B: fixed key, 80 kWh shared; relative key, 84 kWh; optimal key, 100 kWh
Fictitious example, calculated according to the Fluvius protocol. The relative key puts B's share of its own injection back into play; the optimal key also redistributes what B and C did not consume. Click to enlarge.

When a consumer leaves the operation. The same logic applies when Fluvius removes a consumer from the operation, for example after a move or when its mandate is withdrawn. Its percentage is set to zero. With a fixed key, the corresponding part of the injection is no longer distributed and goes back to the producers. With a relative or optimal key, the percentages of the remaining participants are applied proportionally: in the example, if C leaves, B's 40% and D's 30% become 57.1% and 42.9%. In every case, the manager of the operation is notified and can adjust the key.

No custom key, no priority. The choice is limited to these three types, and the protocol provides no order of priority between participants. The percentages themselves remain free.

Declaration and changes. The key is entered in the Mijn Fluvius portal by the manager mandated by the participants. The manager can change both the percentages and the type of key every day; the change takes effect at midnight. A new participant keeps a share of 0% until the key has been adjusted. Fluvius calculates the shared volumes every month; the results are generally available around the 25th of the following month.

In Brussels

Framework. The rules are set out in the Technical Regulation for the electricity distribution grid, approved by the Brussels regulator, Brugel, and in the explanatory note on allocation methods published by Sibelga, the grid operator. CityWatt is one of the energy communities managed by RaYSun. It is the main one in Brussels: it hosts the largest number of sharing operations, including Energilia Brussels.

Three methods, one of which has two variants. In Brussels, the term used is allocation method rather than key.

Example. In one quarter hour, 100 kWh are injected and four participants consume 10, 20, 40 and 60 kWh. With equal shares in one round, 80 kWh are shared. The three other methods share all 100 kWh, but not in the same way: the allocation in several rounds gives as much to C as to D, the pro rata allocation follows each one's consumption, and the hybrid allocation, here with the whole injection put into play in the first round, lies in between.

Four calculations over the same quarter hour in Brussels, for 100 kWh injected: fixed allocation in one round, 80 kWh shared; fixed in several rounds, pro rata and hybrid, 100 kWh shared, with different shares for participants C and D
Fictitious example. The last three methods share the whole injection, but do not split it the same way between participants C and D. Click to enlarge.

One priority category. Whatever the method, one category of participants can be served first, for example the meters of the common areas of a building. The rest of the injection is then allocated to the other participants according to the chosen method. Only one priority category is possible at present.

Other methods. The Technical Regulation allows Sibelga to set new allocation methods, depending on their feasibility, on its own initiative or following a request.

Declaration and changes. The method is stated in the sharing form, submitted at least five working days before the desired start date. If it is complete, Sibelga validates it within five working days, and sharing starts on the first day of a month. The method can then be adjusted at any time: the adjustment takes effect on the first day of the following month.

Change under way. From 11 December 2025 to 31 January 2026, Sibelga held a public consultation on several proposals to change these methods. On the publication date of this article, the methods resulting from that consultation had not yet been published: the rules described above are those of the documents in force.

Comparison of the three Regions

WalloniaFlandersBrussels
Standard keys Equal fixed, specific fixed, dynamic pro rata Fixed, relative, optimal Fixed in one or several rounds, pro rata, hybrid
Calculation rounds per quarter hour Three iterations at most, one key per iteration A single calculation (fixed, relative); iterations until nothing is left (optimal) One round (fixed, pro rata), two rounds (hybrid), until nothing is left (fixed in several rounds)
Priority First iteration with priority, or even exclusive No order of priority provided One priority category, served first
Other key Possible, after a feasibility review by the grid operator No, three types only New methods set by Sibelga, depending on their feasibility
Changes Form and amendment, up to 50 working days Every day in Mijn Fluvius, effective at midnight At any time, effective on the first day of the following month
Reference text CWaPE list of standard keys, order of 17 March 2023 Fluvius energy sharing protocol, version 3.2 Technical Regulation, articles 4.61 to 4.71, and Sibelga note

How to choose a key

The choice depends on the goal the participants set themselves.

This choice is prepared on the participants' actual consumption and production curves. That is the role of the manager of the operation: RaYSun designs sharing operations on the basis of these profiles, declares the key to the grid operator and keeps it up to date.

Sources

To go further: our guide to energy communities in Belgium and the My Community monitoring platform, where each participant can see its shared volumes quarter hour by quarter hour.

← All articles

WANT TO KNOW MORE?

See how much your organisation could save

→ Book a discovery call